City Alerts, Main Street Project|

Main Street from Badger Street to Fulton Street will be closed to vehicle traffic. Pedestrian traffic is allowed and we will make accommodations to allow pedestrians through. The Fulton Street intersection will remain open to vehicle traffic going westbound, eastbound, and northbound.
 
The first week of the closure will consist of saw cutting, surveying, setting up erosion control, and start with roadway pavement removal.

N. Main Street from Fulton to Granite Street is open. We will still make progress on this section. Flower pots were placed, benches should arrive next week. Trash cans will also be installed in the near future.
 
A reminder on some of the changes to this section of N Main Street.
 
·     Sessions St from the alleyway to N Main is a one-way for east-bound traffic only. The benefits for this new alignment include; additional parking on Sessions, safer pedestrian crossings, and promote more traffic to the northern blocks.
 
·     Another change is the Granite/Cooper/Water Street intersection with N. Main Street. This intersection is now a 4-way stop controlled intersection. The benefits for this to increase safety by slowing vehicle traffic and improving pedestrian crossings.