Work on Harrison Street started mid-week with saw cutting and crews starting replacement of the old water laterals. Lateral replacement will continue next week. The construction zone is closed for all traffic with the exception of the residents who live in the construction zone.
Work on High Street saw a lot of progress. The grading crew will continue into next week as the crew progresses down the hill towards Highland Drive. Please be careful a most of the sidewalk and curb and gutter is missing on Highs Street.