High & Harrison Project|

The paving crew has stayed on track and will place new asphalt on High Street starting tomorrow (9/8).  The new asphalt will be placed in two layers, tomorrow, the first of two layers will be placed and compacted.  The crew will take up about half of the road with dump trucks dumping material into a paving machine which places the new asphalt and is then followed by a couple rollers that compact the asphalt to give it strength.   We ask that vehicles stay off the asphalt until the crew is done.  Also, any cars should not be kept on the grade overnight as work will start as early as 7am.   Work on Harrison Street continues with more concrete work that will continue through the end of the week.   Please contact me at (715) 258-4420 or jberrens@cityofwaupaca.org with any questions or concerns.  