High & Harrison Project|

All asphalt work is complete on High Street!  We will start placing topsoil next week in the boulevards and areas disturbed by the utility work.  High Street will remain closed to all traffic except for those that live on the project.  We still need to complete topsoil work and paint new pavement markings.  Until that work is complete, barricades at the end of the project will remain in place.  All driveways should be open for use.

Work on Harrison Street will start again next week.  We should see a milling machine arrive by mid-week to grind down the existing asphalt from Fulton Street to Granite Street.  Once the existing cracks and bumps are removed, the paving crew will place a new layer of asphalt over the top.