High Street and Harrison Street reconstruction project 2022 (10/7/2022) update

High & Harrison Project|

Topsoil work is complete.  Seed and hay is nearly done with just a little remaining in the narrow... Read More → High Street and Harrison Street reconstruction project 2022 (10/7/2022) update

High Street and Harrison Street reconstruction project 2022 (9/23/2022) Paving Update

High & Harrison Project|

Topsoil, seed, and hay was placed on High Street from Fulton to just south of Union Street.  It was also... Read More → High Street and Harrison Street reconstruction project 2022 (9/23/2022) Paving Update

High & Harrison Street Update 9.16.22

High & Harrison Project|

All asphalt work is complete on High Street!  We will start placing topsoil next week in the boulevards... Read More → High & Harrison Street Update 9.16.22

High & Harrison Update 9.9.22

High & Harrison Project|

The paving crew finished the first of two layers of asphalt on High Street.  Barring weather and... Read More → High & Harrison Update 9.9.22

High Street and Harrison Street reconstruction project 2022 (9/7/2022) Paving Update

High & Harrison Project|

The paving crew has stayed on track and will place new asphalt on High Street starting tomorrow (9/8).  The... Read More → High Street and Harrison Street reconstruction project 2022 (9/7/2022) Paving Update

High Street and Harrison Street reconstruction project 2022 (8/26/2022)

High & Harrison Project|

More concrete poured on High Street! Concrete crews continued making good progress by forming up and pouring... Read More → High Street and Harrison Street reconstruction project 2022 (8/26/2022)

High & Harrison Update 8.19.22

High & Harrison Project|

A lot of work was completed this past week! All of the curb and gutter was placed on High Street.  Now... Read More → High & Harrison Update 8.19.22

High & Harrison Project Pictures 8.17.22

High & Harrison Project|

... Read More → High & Harrison Project Pictures 8.17.22

High & Harrison Update 8.12.22

High & Harrison Project|

Work on Harrison Street water laterals continued again this past week. There is all but one lateral to... Read More → High & Harrison Update 8.12.22

High & Harrison Update 8.5.22

High & Harrison Project|

Work on Harrison Street started mid-week with saw cutting and crews starting replacement of the old water... Read More → High & Harrison Update 8.5.22